On Going Projects

Project Name:
Pave Lester Road from Vick Road to Rock Springs Road

Managing Division:
Design Engineering

Construction By:
Public Services Utility Construction Crew

Project Status-Expected Completion Date:
Road open for traffic June 30, bike path open by the end of July

Project Update:
The Lester Road extension, from Vick Road to Rock Springs Road opened on Monday, June 30.

The extension of Lester Road includes a 2-lane road, with left-turn lanes at the intersection of Rock Springs Road, as well as Vick Road, plus a bike path, and new traffic signal located at Lester Road and Rock Springs Road. 

While the road is open, the bike path is not. The City is expecting to take delivery of protective fencing for the path in the coming week, and installation will occur upon delivery. The bike path is slated to open for use by the end of the month.

Police ask that travelers observe the 35 MPH speed limit when commuting on Lester Road, and allow for additional travel time on Rock Springs Road to accommodate the new traffic signal.

Additional questions regarding the project may be addressed to Public Services, 407-703-1731.



Photo Update: 6/14/14
Lester Road 6.14


Project Name:
Downtown Regional Stormwater Facility/Martin's Pond Improvements

Managing Division:
Design Engineering

Construction By:
To Be Determined

Project Status-Expected Completion Date:
Phase One of the project began in January 2014, expected to be complete in May. Phase Two should begin in September 2014 (Phaste Two to include construction of the boardwalk, sidewalk, landscaping, and fountain).

Project Update:
The new, decorative fence is currently being installed along Hwy 441. Contractor is performing work on the right-of-way along the north side of 6th Street. In addition, dirt is being removed from the bottom of the pond. Weather is a controlling factor with regard to how quickly work will be completed.

Photo Update: 6/14/14
pond 6.14


 Project Name:
Votaw Road-12" Water Main Extension

Managing Division:
Design Engineering

Construction By:
Public Services Utility Construction Crew

Project Status-Expected Completion Date:
To Be Determined


Project Name:
Sheeler Avenue-Utility loop system for potable water

Managing Division:
Design Engineering

Construction By:
Public Services Utility Construction Crew

Project Status-Expected Completion Date:
To Be Determined





 